FG TERMINATES UNDERPERFORMING ABUJA-LOKOJA ROAD CONTRACTS FOR POOR PERFORMANCE
The Federal Ministry of Works has cancelled multiple contracts on the Abuja-Lokoja highway after contractors failed to meet timelines despite massive delays some exceeding 188% of scheduled time with under 2% completion. Minister David Umahi announced mutual terminations for projects like culverts/drains by Sadogi Nigeria Ltd (39% done, 113% time elapsed), Abuja-Lokoja Section 4A by…